Center for Changing Lives Progress Updates

Webcam: click here to watch building site live
Building fly-around simulation
The $27 million, 112,000 square-foot Center for Changing Lives (CFCL) was designed by BKV Architects and is being built by Weis Builders. The Center is actually two connected buildings; a service center and a housing complex. The new service center will house LSS mental health counseling services, wellness services, housing services, financial services, adoption services, refugee services and employment services. It will also house Kaleidoscope, an after-school program for kids, and the new offices and sanctuary for Messiah Lutheran Church.

All 48 units of housing are affordable, with 38 units targeted for households earning up to 45% area median income and the remaining ten units targeted for households earning up to 15% area median income. Thirteen apartments are specifically designated for households experiencing long-term homelessness or near homelessness. These households will pay no more than 30% of their income towards rent.

The CFCL will be a LEED Certified building when completed. LEED Certification is a rating system developed by the U.S. Green Building Council that guides environmentally-sustainable construction. For example, the affordable-housing portion of the CFCL will include a variety of green features that will benefit both the residents and the surrounding community.

November 17: Construction complete

Construction of the Park Avenue Apartments was completed on September 1. Weis Builders turned the building over to LSS that day. Most units are currently occupied.

Construction of the Center for Changing Lives, where LSS services and staff reside, is complete. Staff have moved into the building and are offering services to clients at that location. Weis is working on some owner-requested additions.

September 18: Tenants move into the apartments as the Center nears completion

Construction of the Park Avenue Apartments was completed on September 1. Weis Builders turned the building over to LSS that day, and tenants have been moving in steadily. Weis has been working on some owner-requested additions.

Construction of the Center for Changing Lives, where LSS services and staff will reside, is currently on schedule. The site is south of 24th Street, west of Park Avenue, and east of Oakland Avenue in south Minneapolis. The latest status report is below.

Status as of September 18:

  • Interior mechanical/electrical rough-in is 90% complete
  • Drywall on interior walls is 99% complete
  • Rain gardens/sitework is 90% complete
  • Painting is 60% complete
  • Exterior windows have been installed
  • Ceramic tile in bathrooms is 90% complete
  • Acoustical ceilings are 25% complete

August 5: Tenant move-in starts in less than a month

Construction of the Center for Changing Lives is currently on schedule. The site is south of 24th Street, west of Park Avenue, and east of Oakland Avenue in south Minneapolis. The latest status report is below.

Completed:

  • Excavation
  • Footings and foundation walls
  • Precast (garage columns and ceiling)
  • Steel structure
  • Exterior wall framing, sheathing, and brick
  • Interior stud walls
  • Roofing
  • 5th-floor mock unit

In progress:

  • Interior drywall
  • Interior mechanical systems
  • Rain gardens
  • Painting
  • Exterior windows

Future milestones:

  • Park Avenue Apartments complete (September 1)
  • Center for Changing Lives service center complete (November 17)

July 2: Focus moves to interior framing, systems, and drywall

Construction of the Center for Changing Lives is currently on schedule. The site is south of 24th Street, west of Park Avenue, and east of Oakland Avenue in south Minneapolis. The latest status report is below.

Completed:

  • Excavation
  • Footings and foundation walls
  • Precast (garage columns and ceiling)
  • Steel structure
  • Exterior wall framing, sheathing, and brick
  • Roofing

In progress:

  • Interior framing and drywall
  • Interior mechanical systems

Future milestones:

  • Landscaping (August)
  • Park Avenue Apartments complete (September)
  • Center for Changing Lives service center complete (November)

June 5: Exterior work nears completion

Construction of the Center for Changing Lives is currently on schedule. The site is south of 24th Street, west of Park Avenue, and east of Oakland Avenue in south Minneapolis. The latest status report is below.

Completed:

  • Excavation
  • Footings and foundation walls
  • Precast (garage columns and ceiling)
  • Steel structure
  • Exterior wall framing and sheathing

In progress:

  • Roofing
  • Exterior brick

Future milestones:

  • Interior drywall (July)
  • Landscaping (August)
  • Park Avenue Apartments complete (September)
  • Center for Changing Lives service center complete (November)

May 14: Exterior brick work in full swing

Construction of the Center for Changing Lives is currently on schedule. The site is south of 24th Street, west of Park Avenue, and east of Oakland Avenue in south Minneapolis. The latest status report is below.

Completed:

  • Excavation
  • Footings and foundation walls
  • Precast (garage columns and ceiling)
  • Steel structure

In progress:

  • Exterior wall framing
  • Exterior sheathing
  • Air moisture barrier
  • Roofing
  • Brick laying

Future milestones:

  • Weather-tight roofing (June)
  • Interior drywall (July)
  • Landscaping (August)
  • Park Avenue Apartments complete (September)
  • Center for Changing Lives service center complete (November)

April 24: Apartment roof soon to be weather tight

Construction of the Center for Changing Lives is currently on schedule. The site is south of 24th Street, west of Park Avenue, and east of Oakland Avenue in south Minneapolis. The latest status report is below.

Service Center Progress:

  • Steel 90% complete
  • Exterior studs 40% complete
  • Exterior sheathing 35% complete
  • Mechanical/electrical rough-in started

Service Center Milestones:

  • Roof weather tight by June 12
  • Interior drywall installation begins July 3
  • Landscaping to occur in August
  • Project complete on November 1
  • Move-in date is November 28

Park Avenue Apartments Progress:

  • 5th floor wall panels complete
  • Roof trusses started
  • Mechanical rough-ins on 3rd and 4th floor started

Park Avenue Apartments Milestones:

  • Roof weather tight by April 30
  • Interior drywall installation begins May 1
  • Landscaping to occur in August
  • Project complete and ready for move-in on September 1

March 31: Steel and wood framing continues

Construction of the Center for Changing Lives is currently on schedule. The site is south of 24th Street, west of Park Avenue, and east of Oakland Avenue in south Minneapolis. The latest status report is below.

 

Completed:

  • Excavation
  • Footings (cement foundation)
  • Foundations Walls
  • Waterproofing of Foundation Walls
  • Garage Walls
  • Precast (garage columns and ceiling)
  • Elevator Shaft (main & south shaft)
  • Elevator Shaft (south shaft)

In Progress:

  • Steel Structure on CFCL
  • Wood framing on Park Avenue Apartments (PAA)
  • Centrum Window-Wall
  • Exterior wall framing

Future Milestones:

  • Weather Tight Roofing (May)
  • Interior Drywall (July)
  • Landscaping (August)
  • Complete Project (November)

March 5: The steel is going up

Construction of the Center for Changing Lives is currently on schedule. The site is south of 24th Street, west of Park Avenue, and east of Oakland Avenue in south Minneapolis. The latest status report is below.

Completed:

  • Excavation
  • Footings (cement foundation)
  • Foundations Walls
  • Waterproofing of Foundation Walls
  • Garage Walls
  • Precast (garage columns and ceiling)
  • Elevator Shaft (main shaft)

In Progress:

  • Elevator Shaft (south shaft)
  • Steel Structure on CFCL
  • Wood framing on Park Avenue Apartments (PAA)

Future Milestones:

  • Weather Tight Roofing (May)
  • Interior Drywall (July)
  • Landscaping (August)
  • Complete Project (November)